Can Los Angeles afford the growing costs of the convention center expansion?

Over the past year, LA political leaders are looking for a way to upgrade downtown convention centers without providing cuts to core services.

The city’s budget team pushed the facility with digital billboards, which would generate tens of millions of advertising revenue. A city-employed consultant proposed several cost-cutting measures, including eliminating the initial plan as an extension of the public square.

Despite these efforts, the project lost its stance. City Council members were told Tuesday that the price tags rose again to $2.7 billion, an increase of $483 million from six months ago.

Some people at the City Hall are getting nervous that the first phase of the project will not be completed in time at the 2028 Olympics, which jeopardizes the Convention Center’s status as one of the main venues. Beyond that, city officials have begun to publicly worry that Gavin Newsom may not support a state bill that allows the installation of two digital billboards that will face the busy intersection of highways 10 and 110.

The two signs are opposed by groups such as the scenic U.S. – which are expected to generate the vast majority of advertising revenue for the project, according to the city’s budget team.

City Administrative Official Matt Szabo said if state and federal support for the signs fails to come true, the City’s general fund budget will provide an average of $111 million a year in 2058 to cover the cost of the convention center expansion.

The earliest years were the most expensive. For example, in 2031, an estimated $167 million in taxpayer funds will be spent on the debt and operations of the conference center – even after the revenue from the project is included in the revenue.

“The cost has increased significantly since the last time we met in this room,” Szabo said. “Seriously,” [construction] The timeline still exists. The revenue that the project depends on will depend on – Danger. ”

For some on the Council, the latest bad news has proven too much.

Katy Yaroslavsky, head of the Council’s strong budget committee, told The Times that she believes the overhaul of the conference center is key to making the downtown “stronger, more economical and vibrant.” But the current plan is “too expensive” as the city is already struggling to pay for police, street repairs and other basic services.

“Without signage revenue, the risk of the city’s budget is huge and unbearable,” Yaroslavsky said in a statement.

Newsom spokesman Izzy Gardon declined to discuss the Digital Billboard Act, saying the Governor’s Office “usually does not comment on pending legislation.” State Councilor Mark Gonzalez, who represents part of the downtown area, said he “effectively interacts with the News Magazine Administration.”

“I’m confident we’ll find a way forward,” he said.

Szabo said council members must decide whether to continue the project by September 15. Even some of the Council’s urban boosters, their next steps sounded nervous.

“I heard some colleagues say, ‘We want a very beautiful convention center, but a bankrupt city?’” said Ysabel Jurado, a councillor who represents most downtown.

The business group held a rally on expansion, saying it would eventually allow Los Angeles to participate in the big practice while also injecting new life into downtown still under the consequences of the Covid-19 pandemic.

The project also accumulates an organized workforce, especially the construction unions in the area, which will create thousands of jobs.

“With over 800 members unemployed, we need a project like this,” said Zachary Solomon, business representative for International Electric Workers. “The cost of this project will only continue to increase, so we need this project now.”

Many groups supporting the expansion of the Conference Center have played a role in electing the Council members. Nevertheless, if the Council moves forward the project, it will face the main warning signs.

The city’s top policy analyst warns that any major building delay could cause organizers of the 2028 Olympic and Paralympic Games to pull up the convention center, which was scheduled to host judo, wrestling, fences and other competitions, to stand out from its venue list.

“It’s really bad to pay such a premium on such a project. [have] Hosting the Olympics is not ready yet.

Stuart Marks, the citywide senior vice president of the development company that led the conference center project, told council members that he was “very confident” that the work would be completed on time, saying the flexibility of the plan – a significant penalties were imposed if the developer failed to execute.

Marks’s company, who works with the Anschutz Entertainment Group of the Convention Center, said the companies responsible for construction have an established history and work on projects such as Staples Center (now Crypto.com Arena) and the San Francisco expansion Moscone Center.

“Their reputation is coming soon. Our reputation is online.

The proposed timeline requires APCLA (also known as AEG Plenary Conference Los Angeles (a joint venture responsible for overseeing the expansion) to start construction, to start construction, and to stop in the game and then finish the work after the game is over.

According to the proposal, a new wing will connect the Green South Hall, the landmark of the Convention Center, with the Blue West Hall.

Much of the rise in construction prices is attributed to the city’s Department of Water and Electricity, with a higher recent estimate of the relocation of utilities under Pico Boulevard and the relocation costs of several miles of cables and conduits installed.

DWP officials have warned that they lack the personnel to carry out the project and need to hire external labor. They also said that work at the conference center could lead to delays in other projects, including the construction of a new railway line in the San Fernando Valley – as staff must be transferred.

The TSO responded to many of Szabo’s concerns and said in another report that the project would have a “serious negative impact” on the General Fund budget, which paid for police, paramedics responses and other essential services.

Times worker Laura Nelson contributed to the report.